Long Beach port to celebrate final completion of ambitious Middle Harbor project in August – Daily News

on Jul6
by | Comments Off on Long Beach port to celebrate final completion of ambitious Middle Harbor project in August – Daily News |

The Port of Long Beach is planning a celebration for next month to celebrate, after 10 years, the completion of what’s been touted as the world’s most advanced and “greenest” container terminal.

The $1.5 billion Middle Harbor project, which has opened in phases but was formally completed in last month with final work on wharf and backland areas, combined two aging, 1950s-era shipping terminals into one. It brought upgraded wharfs, greater water access, more storage areas, an expanded on-dock rail yard to reduce truck trips and the ability to accommodate the newest and largest ships.

It also has full automation via the project’s Long Beach Container Terminal, where remotely-run cranes glide back and forth and tower over nearby structures as they interface with a computer-controlled stacking system.

Terminal automation isn’t without high financial costs — or controversy. Automation has long been a source of major tension between both the Ports of Long Beach and Los Angeles, and the local longshore unions. The longshore workforce is currently preparing to retrain and adapt to the new systems while keeping a wary eye on potential job losses that could result from the changing operations.

But automation is becoming increasingly common. Two Port of L.A. terminals, for example, now at least partially automated — APM Terminals on Pier 400 and TraPac.

And in May, Pier T terminal operators in the Port of Long Beach called labor union leaders to announce their plans to pursue automation as well.

Both the Ports of Long Beach and L.A. are pushing the accelerator to meet an overall zero-emissions deadline in 2035. A deadline for terminal equipment arrives earlier, in 2030. The ports have been the largest stationary polluters in the region but are making progress under the joint Clean Air Action Plan adopted in 2006 and updated in 2010 and 2017.

The automated electric equipment is pollution free.

Construction on the Middle Harbor redevelopment project began in 2011 and its completion is a major milestone, port officials said at the Long Beach harbor commission meeting last week.

A public ceremony will be held in August, though officials have not yet determined an exact date.



Previous postDodgers’ Manager Dave Roberts Not Expecting Trevor Bauer Back After 7-day Leave – NBC Los Angeles Next postSheriff’s Bomb Squad Safely Render Cache of Illegal Fireworks in Hermosa Beach – NBC Los Angeles


Los Angeles Financial times


Copyright © 2024 Los Angeles Financial times

Updates via RSS
or Email